Wiring stopped
3) & 4) OHE poles with insulators
đ¸Bhanapur
5) & 6) Large SB
đ¸Between Bhanapur and Bannikoppa
7) & 8) Aligned OHE poles without insulators
đšLand levelling done for Talakal - Wadi (Gadag - Wadi) new line
đ¸Bannikoppa
9) Large SB
10) Non-aligned OHE pole and portal
đ¸Between Bannikoppa and Sompur Road
11) Non-aligned OHE pole
đ¸Sompur Road
12) Large SB
đ¸Between Sompur Road and Harlapur
13) to 15) Foundations for OHE poles appeared and disappeared in some stretches
đ¸Harlapur
16) Foundation for OHE pole at Harlapur outer (Koppal end)
17) Foundation for OHE pole at Harlapur outer (Gadag end)
đ¸Between Harlapur and Kanginhal (Electrification & doubling)
18) & 19) Doubling under progress
20) & 21) Foundations for OHE poles were spotted adjacent second line under construction in between Harlapur and Kanginhal
đ¸Kanginhal (Electrification & doubling)
22) Foundation for OHE pole on platform
23) New platform and Foot Over Bridge (FOB) under construction
đ¸Kanginhal - Gadag (Doubling)
24) to 26) Doubling is almost complete in between Kanginhal and Gadag outer
Pictures source: Self