बैलास्ट पैकिंग का काम पूरा सफल रहा ट्रायलAfter 17 days of repair work, a trial run was conducted on the Pilibhit-Mailani railway track on Thursday. The repair work was carried out after a culvert between Mala Shahgarh and Pilibhit-Puranpur railway track collapsed due to heavy rainfall on July 8th. The trial run was successful, and the engineers...
more... have sent a report to the divisional officials. Trains are expected to resume operations on Friday, pending approval from the Divisional Railway Manager (DRM). The train from Kathgodam to Howrah, originally scheduled for July 25th, was postponed due to the repair work and will now depend on the DRM's decision.
Pilibhit-Mailani railway track pe 17 din ke repair work ke baad, Thursday ko trial run kiya gaya. July 8 ko heavy rainfall ki wajah se Mala Shahgarh aur Pilibhit-Puranpur railway track ke beech ek culvert collapse ho gaya tha. Trial run successful raha, aur engineers ne divisional officials ko report...
more... bhej di hai. DRM ke approval ke baad, Friday se trains ka operation resume ho sakta hai. Kathgodam se Howrah jaane wali train, jo July 25 ko chalni thi, repair work ki wajah se postpone ho gayi thi aur ab DRM ke decision pe depend karegi.