NAGPUR-WARDHA 3rd &4th line
Total 78.71 km
Cost 540.02 Crs
Land Acquisition-36.47 Hectare (99.68% completed)
...
more...
A)Completed sections-19.33 km
Butibori-Borkhedi-Sindi
B)Near completion sections-42.40 km
(Likely commissioning this year)
Ajni- Butibori
Sindi-Seloo